Subject: 10.3 (Item #14) Final Change Order: Taber Construction, Inc.
LCAP (Local Control Accountability Plan) Goal:
Policy:
Enclosure
File Attachment:
1601sum.pdf
Summary: On March 12, 2012 the Board of Education awarded Bid #1601 to Taber Construction, Inc. for $3,800,000.00 for heating, ventilating and air conditioning (HVAC)renovations at Sun Terrace and Sequoia Elementary Schools and Valley View Middle School.

As aresult of a need to: 1)perform additional unforseen hazardous materials abatement; 2)implement design adjustments to respond to concealed utilities; and 3) implement minor electric, mechanical and structural modifications staff is recommending a single, final additive change order in the amount of $96,668.00. This single, final change order constitutes a 2.54% change in contract and will result in a final contract value of $3,896,668.00.
Funding: 2010 Measure C Funds
Fiscal Impact $96,668.00
Recommendation: Approve final change order as presented
Approvals:
Recommended By:
Signed By:
Pete Pedersen - Measure C
Signed By:
Steven Lawrence - Superintendent
Vote Results:

New Motion
Member Linda Mayo Moved, Member Brian Lawrence seconded to approve the New motion 'Approve final change order as presented

Motion to approve the Final Change Order: Taber Construction, Inc. as presented.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Linda Mayo     Yes
Lynne Dennler     Yes
Cheryl Hansen     Yes
Brian Lawrence     Yes
Barbara Oaks     Yes