Meeting Date:
|
12/10/2012 - 7:00 PM
|
Category:
|
Consent Items Pulled for Discussion
|
Type:
|
Action
|
Subject:
|
10.3 (Item #14) Final Change Order: Taber Construction, Inc.
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On March 12, 2012 the Board of Education awarded Bid #1601 to Taber Construction, Inc. for $3,800,000.00 for heating, ventilating and air conditioning (HVAC)renovations at Sun Terrace and Sequoia Elementary Schools and Valley View Middle School. As aresult of a need to: 1)perform additional unforseen hazardous materials abatement; 2)implement design adjustments to respond to concealed utilities; and 3) implement minor electric, mechanical and structural modifications staff is recommending a single, final additive change order in the amount of $96,668.00. This single, final change order constitutes a 2.54% change in contract and will result in a final contract value of $3,896,668.00.
|
Funding:
|
2010 Measure C Funds
|
Fiscal Impact
:
|
$96,668.00
|
Recommendation:
|
Approve final change order as presented
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Pete Pedersen - Measure C
|
|
Signed By:
|
|
Steven Lawrence - Superintendent
|
|
|
|
Vote Results:
|
New Motion | Member Linda Mayo Moved, Member Brian Lawrence seconded to approve the New motion 'Approve final change order as presented Motion to approve the Final Change Order: Taber Construction, Inc. as presented.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Lynne Dennler | Yes | Cheryl Hansen | Yes | Brian Lawrence | Yes | Barbara Oaks | Yes | |
|
|
|
|
|
|