Subject: 16.14 Final Change Order for Bid #1618; Contract #C-914 Measure-C Secondary schools technology improvements - Structured Cabling, Adding Ethernet Drops w/Fiber Backbone in Middle Schools and High schools, between MDUSD & Walker Telecomm. Inc.
LCAP (Local Control Accountability Plan) Goal:
Policy:
Enclosure
File Attachment:
1618_FCO_6-3-2013.pdf
Summary: On November 5,2012, the Board of Education awarded Bid #1618 to Walker Communication,Inc. for $1,094,141.00 for the provision of all tools, materials, labor and equipment necessary to provide Structured Cabling, Adding Ethernet Drops in Classrooms with Fiber Optic Backbone at College Park HS, Mt. Diablo HS, Oak Grove MS, Riverview MS, Northgate HS, Concord HS, Ygnacio Valley HS, Clayton Valley HS, Sequoia MS, El Dorado MS, Foothill MS, Loma Vista Adult Center, Diablo View MS, and Valley View MS.

Due to additional scope for site use changes, unforeseen conditions and non-functioning portions of the existing backbone at multiple sites a final change order in the amount of $73,835.90 is necessary. The single, final change order will result in a revised contract value of $1,167,976.90.
Funding: 2010 - Measure - C
Fiscal Impact $73,835.90
Recommendation: Approve Final Change Order as Submitted
Approvals:
Recommended By:
Signed By:
Tim Cody - Program Manager
Signed By:
John Bernard - Interim Superintendent
Vote Results: