8.36 (Item 36) Notice of Completion for Bid #1555
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
Bid/RFQ #1555 was called to provide Fencing Improvements at Clayton Valley High School. The lowest responsible, responsive bidder was Chain Link Fence and Supply, Inc. for the contract amount of $37,476.00. The scope of work included, but was not limited to site work, concrete paving, asphalt concrete, fencing and gates. There was an additive change order in the amount of $30,503.00. Work and services for the project have been satisfactorily completed for a final contract value of $67,979.00. Budget for this project: $45,000.00.
|
Funding:
|
Proposition 55
|
Fiscal Impact
:
|
None
|
Recommendation:
|
Approve Notice of Completion as presented.
|