Meeting Date:
|
9/24/2012 - 6:30 PM
|
Category:
|
Consent Agenda
|
Type:
|
Action
|
Subject:
|
9.18 (Item #19) Notice of Completion for Bid #1612/C-910, DecoTech Systems, Inc.: Electrical and HVAC Upgrades to Main and Intermediate Distribution Frames
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
Bid No. 1612 was called to provide Electrical, HVAC Upgrades to Main and Intermediate Distribution Frames at Multiple Sites. The lowest responsible bidder was DecoTech Systems, Inc. for the base bid award amount of $156,000.00. The scope of work included, but was not limited to: Electrical, HVAC Upgrades to Main Distribution Frames and Intermediate Distribution Frames at Clayton Valley HS, College Park HS, Northgate HS, Concord HS, Mt. Diablo HS, Ygnacio Valley HS, Diablo View MS, Foothill MS, Riverview MS, and Loma Vista Adult Center. There was an additive change order on this project in the amount of $9,036.00. Work and services for this project have been satisfactorily completed for a total expenditure of $165,036.00. Budget for this project: $194,388.00
|
Funding:
|
2010 Measure C
|
Fiscal Impact
:
|
|
Recommendation:
|
Approve Notice of Completion as presented.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Laura Warner - Administrative Secretary
|
|
Signed By:
|
|
Pete Pedersen - Measure C
|
|
Signed By:
|
|
Greg Rolen, Esq. - General Counsel
|
|
Signed By:
|
|
Bryan Richards - Chief Financial Officer
|
|
Signed By:
|
|
Steven Lawrence - Superintendent
|
|
|
|
|
|
|
|