Meeting Date:
|
9/25/2013 - 7:30 PM
|
Category:
|
Consent Agenda
|
Type:
|
Action
|
Subject:
|
8.17 (Item #18) Final Change Order for LLB Project # 1637 for painting at various elementary school sites (Shore Acres, Bel Air & Rio Vista).
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On June 3, 2013, the Board of Education awarded a Lease/Lease-back Agreement for MDUSD Project #1637 with Diamond Painting Co. KK. for a Guaranteed Maximum Project Cost of $225,000.00 for 3 Elementary Schools MDUSD Project # 1637 Paint Package #1 at Bel Air Elementary School, Shore Acres Elementary School and Rio Vista Elementary School. As a result of the need for: 1) Excessive Prep work due to flaking stucco and patch for the MU and various walls at Shore Acres Elementary school; 2) Return of un-used contingency fund, staff is recommending a single, final DEDUCTIVE change order in the amount of ($5,290.00). This single, final change order constitutes the return of approximately 79% of contingency and .65% contract changes and will result in a final contract value of $219,710.00.
|
Funding:
|
Proposition 55
|
Fiscal Impact
:
|
($5,290.00)
|
Recommendation:
|
Approve as Recommended
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
John Willford - Assistant Program Manager
|
|
Signed By:
|
|
Tim Cody - Program Manager
|
|
Signed By:
|
|
John Bernard - Interim Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Moved, Member seconded to approve the Original motion 'Approve Consent Agenda.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Barbara Oaks | Yes | Linda Mayo | Yes | Cheryl Hansen | Yes | Lynne Dennler | Yes | Brian Lawrence | Yes | |
|
|
|
|
|
|