Review Agenda Item
Meeting Date: 10/26/2010 - 7:30 PM
Category: Consent Agenda
Type: Action
Subject: 8.26 (Item 27) Additive Change Order For Bid #1559/Contract C-898
LCAP (Local Control Accountability Plan) Goal:
Policy:
Enclosure
File Attachment:
Summary: Bid No. 1559 was called to provide the Telephone and Intercom Upgrades at Foothill Middle School. The lowest responsible bidder was Sedge Electric, Inc. for the bid award amount of $243,700.00. The scope of work included, but was not limited to: removal and replacement of telephone and intercom systems.

As a result of unforeseen conditions due to additional underground trenching, an additive change order in the amount of $2,539.00 was issued. This additive change order will result in a final contract value of $246,239.00.

Budget for this project: $280,000.00.
Funding: Deferred Maintenance
Fiscal Impact $2,539.00
Recommendation: Approve Additive Change Order as presented.
Approvals:
Recommended By:
Signed By:
Joanie Peterson - Buyer
Signed By:
Greg Rolen, Esq. - General Counsel
Signed By:
Bryan Richards - Chief Financial Officer
Signed By:
Steven Lawrence - Superintendent