Review Agenda Item
Meeting Date: 5/21/2012 - 7:00 PM
Category: Consent Items Pulled for Discussion
Type: Action
Subject: 10.2 (Item #10) Award of Design Services Contract For Refurbishment/Modification of Existing Auto/Metal Shop at Northgate High School-'Project Lead The Way' Engineering Pathway
LCAP (Local Control Accountability Plan) Goal:
Policy:
Enclosure
File Attachment:
MISA0037-%20PHd%20Contract%20Northgate%20HS%20Project%20Lead%20the%20Way%20r[1].pdf
Certificate%20of%20Insurance%20for%20PHD%20Architects%20thru%204-22-13[1].pdf
Summary: On June 28, 2011 the Board of Education approved facility enhancements for each of the comprehensive high schools and Olympic High School. As part of this greater approval the Board approved funding for facility modifications and technologies necessary to support the 'Project Lead The Way' program at Northgate High School. Staff has negotiated, and is now recommending that a fully inclusive 'not to exceed' contract for $18,900.00 be awarded to PHd Architects for comprehensive engineering, design and contract administration services necessary for the approval and satisfactory completion of his project.
Funding: 2010 Measure C Funds
Fiscal Impact $18,900.00
Recommendation: Approve design services contract as presented.
Approvals:
Recommended By:
Signed By:
Pete Pedersen - Measure C
Signed By:
Steven Lawrence - Superintendent
Vote Results: