Subject: 15.18 Award of Design Services Contract for the Construction of New Chemistry Classroom Buildings at Clayton Valley and Mt. Diablo High Schools
LCAP (Local Control Accountability Plan) Goal:
Policy:
Enclosure
File Attachment:
MISA0018-PHDC Contract Measu .pdf
PHD Certificate of Insurance thru 04-22-12.pdf
Summary: Assuming the Board of Education affirms and approves the Facility Enhancement projects prioritized and submitted by both Clayton Valley and Mt. Diablo High Schools, District staff is recommending that a professional services contract for the engineering and design services necessary for the site adaptation and construction of new chemistry classroom buildings at these two sites be approved as soon as possible. Staff has negotiated, and is now recommending that a 'not to exceed' contract in the amount of $136,000.00 be awarded to PHd Architects for the provision of comprehensive engineering, design and contruction administration services required for the approval and satisfactory completion of these proposed facilities.
Funding: $3,000,000.00:
Fund 11: $636,594.00
Fund 17: $2,363,406.00
Fiscal Impact $136,000
Recommendation: Aprrove award of design services contract as presented.
Approvals:
Recommended By:
Signed By:
Pete Pedersen - Measure C
Signed By:
Greg Rolen, Esq. - General Counsel
Signed By:
Steven Lawrence - Superintendent
Vote Results:

Original Motion
Member Linda Mayo Moved, Member Cheryl Hansen seconded to approve the Original motion 'Approve award of design services contract as presented.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Gary Eberhart     Yes
Linda Mayo     Yes
Sherry Whitmarsh     Yes
Lynne Dennler     Yes
Cheryl Hansen     Yes