Subject:
|
14.25 (Item #25) Final Change Order for Bid #1826/C978 with Pinguelo Construction, Inc., for Window Replacements at Mt. Diablo High School
|
LCAP (Local Control Accountability Plan) Goal:
|
Goal 1: All students will receive a high quality education in a safe and welcoming environment with equitable and high expectations, access to technology, and instruction in the California State Standards that prepare them for college and career.
|
Enclosure
|
Bid 1826 Final Change Order
|
File Attachment:
|
|
Summary:
|
On March 25, 2019, the Board awarded Bid 1826 to Pinguelo Construction, Inc., in the amount of $105,000.00 for the Window Replacements at specified District sites. During construction, it was discovered that the following additional work was required. 1. Added laminated glass on the Academic Wing & stairwells. 2. Added panes to Shop Building including window film. The final charge order will result in a contract value of $113,298.98, an increase of $8,298.98 which is an increase of 7.90% of the original contract.
|
Funding:
|
5190 – Routine Restricted
|
Fiscal Impact
:
|
$8,298.98 - The project total is within budget; no additional funds needed.
|
Recommendation:
|
Approve Final Change Order for Bid #1826/C978 with Pinguelo Construction, Inc., for Window Replacements at Mt. Diablo High School in the amount of $8,298.98.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Marie Hill - Senior Secretary
|
|
Signed By:
|
|
Elizabeth McClanahan - Director of Purchasing and Warehouse
|
|
Signed By:
|
|
Melanie Koslow - Director of Maintenance and Operations
|
|
Signed By:
|
|
Richard Jackson - Director of Maintenance, Operations & Facilities
|
|
Signed By:
|
|
Mika Arbelbide - Director of Fiscal Services
|
|
Signed By:
|
|
Rose Ramos - Chief Business Officer
|
|
Signed By:
|
|
Robert Martinez - Superintendent
|
|
|
|
|
|
|
|