Meeting Date: 10/9/2013 - 7:30 PM
Category: Consent Agenda
Type: Action
Subject: 12.14 (Item #15) Notice of Completion for Lease/Leaseback #1642
LCAP (Local Control Accountability Plan) Goal:
Strategic Initiative 5.3 Optimal Operations and Infrastructure
Ensure that our facilities and infrastructure support and enhance student learning and safety.
Policy:
Enclosure
File Attachment:
LLB 1642 NOC.pdf
Summary: L/LB #1642 was called to provide Remodeling of the Art Classroom at Northgate High School. The lowest responsible bidder was E.F. Brett & Company, Inc., for the award amount of $267,917.00. The scope of work included, but was not limited to: Remodeling the Art Classroom from the existing Auto and Metal Shop, and appurtenant facilities to be performed on portions of the School Site.

There was a deductive change order on this project in the amount of $12,758.00. Work and services for this project have been satisfactorily completed, according to the District's Drawings and Specifications, for a total expenditure of $255,159.00.
Funding: Measure C 2010
Fiscal Impact
Recommendation: Approve Notice of Completion as presented.
Approvals:
Recommended By:
Signed By:
Laura Warner - Administrative Secretary
Signed By:
Tim Cody - Program Manager
Signed By:
Jayne Williams - Interim General Counsel
Signed By:
Bryan Richards - Chief Financial Officer
Signed By:
Dr. Nellie Meyer - Superintendent
Vote Results:

Original Motion
Member Moved, Member seconded to approve the Original motion 'Approve attached recommendations.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Barbara Oaks     Yes
Linda Mayo     Yes
Cheryl Hansen     Yes
Brian Lawrence     Yes
Lynne Dennler     Yes