Meeting Date:
|
10/9/2013 - 7:30 PM
|
Category:
|
Consent Agenda
|
Type:
|
Action
|
Subject:
|
12.13 (Item #14) Final Change Order for LLB Project #1642 - Remodel of Art Classroom (Auto/Metal Shop) at Northgate High School
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On June 17, 2013 the Board of Education awarded Lease Leaseback Agreement #1642 to E.F. Brett Company for a Guaranteed Maximum Project Cost of $267,917.00 for the provision of all tools, materials, labor and equipment necessary to remodel the Art Classroom (Auto/Metal Shop) at Northgate High School. As a result of unused contingency, a single, final deductive change order in the amount of ($12,758.00) is necessary. This single, final change order will result in a final, revised contract value of $255,159.00. This final change order represents a decrease of 5% to original contract value.
|
Funding:
|
2010 Measure C
|
Fiscal Impact
:
|
($12,758.00)
|
Recommendation:
|
Approve final change order as presented
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Mitchell Stark - Program Manager
|
|
Signed By:
|
|
Tim Cody - Program Manager
|
|
Signed By:
|
|
Dr. Nellie Meyer - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Moved, Member seconded to approve the Original motion 'Approve attached recommendations.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Brian Lawrence | Yes | Cheryl Hansen | Yes | Lynne Dennler | Yes | Barbara Oaks | Yes | Linda Mayo | Yes | |
|
|
|
|
|
|