Subject:   9.8 (Item #8) Final Change Order: Bid #1600-HVAC Renovations at Loma Vista Adult and Concord High School
Strategic Plan
Policy:  
Enclosure
File Attachment:  
Final Change Order Cover Page Bid 1600[1].pdf
Summary On March 12, 2012 the Board of Education awarded Bid #1600 to Bell products, Inc. for $2,850,000 for the provision of all tools, materials, labor and equipment necessary to complete the installation of new heating, ventilation and air conditioning systems at Concord High School and Loma Vista Adult Center.

As a result of a need to 1)relocate/re-rout low and high voltage circuitry; 2)implement minor mechanical design modifications; 3) perform additional demolition work; 4)implement modifications for relocation of equipment pad; and 4) address unforeseen abatement needs, a single, final change order in the amount of $49,004.00 is necessary. The single, final change order will result in a final, revised contract value of $2,899,004.00. The final change order represents a 1.72% increase to original contract value.
Funding Proposition 55 Funds: $12,056
2010 Measure C Funds: $36,948
Fiscal Impact $49,004.00
Recommendation Approve final change order as presented
Approvals:  
Recommended By:
Signed By:
Pete Pedersen - Measure C
Signed By:
Steven Lawrence - Superintendent
Vote Results:  

Original Motion
Member (Linda Mayo) Moved, Member (Gary Eberhart) seconded to approve the Original motion 'Approve Consent Agenda.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.