Meeting Date:   6/25/2012 - 7:30 PM
Category:   Consent Items Pulled for Discussion
Type:   Action
Subject:   10.4 (Item #38) Measure C High School Project Lists
Strategic Plan
Policy:  
Enclosure
File Attachment:  
Facilities Priority List.pdf
Project List Alt Ed Sites.pdf
Summary At the April 23, 2012 Board meeting, the Board approved $40 million to be allocated between the six comprehensive high schools for facilities improvement projects. Attached is the list for Mt. Diablo High School and the Alternative Education sites.
Funding Measure C Funds
Fiscal Impact
Recommendation Approve as presented.
Approvals:  
Recommended By:
Signed By:
Loreen Joseph - Secretary to the Superintendent
Signed By:
Steven Lawrence - Superintendent
Vote Results:  

Original Motion
Member (Linda Mayo) Moved, Member (Lynne Dennler) seconded to approve the Original motion 'Approve as presented.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion CARRIED 5 - 0
   
Cheryl Hansen     Yes
Gary Eberhart     Yes
Linda Mayo     Yes
Lynne Dennler     Yes
Sherry Whitmarsh     Yes