Summary Bid No. 1561 was called to provide the SMART Classrooms at Concord and College Park High Schools. The lowest responsible bidder was Magnum Construction, Inc., for the bid award amount of $1,654,725.00.

The scope of work included, but was not limited to: site work, demolition and metal stud construction necessary for new modular classroom(s) and laboratory buildings, including associated civil, architectural, structural, plumbing, mechanical and/or electrical work. Generally, these categories involve new finishes, adaptive re-use and modification of certain selected areas, new cabinetry (including laboratory), handicap accessibility, roofing, and photovoltaic systems and pertain to changing and expanding selected infrastructure utilities, and/or extensive modifications. The project involved phasing and barricading work areas. Contractor was responsbile for all work, as well as wiring, system integration, data terminations, connections and photovoltaic systems.

There was an additive change order on this project in the amount of $10,894.49. Work and services for this project have been satisfactorily completed for a total expenditure of $1,665,619.49.

Budget for this project: $2,293,850.00
Funding Proposition 55
Fiscal Impact None
Recommendation Approve Notice of Completion as presented.
Approvals:  
Recommended By:
Signed By:
Joanie Peterson - Administrative Secretary
Signed By:
Bryan Richards - Chief Financial Officer
Signed By:
Greg Rolen, Esq. - General Counsel
Signed By:
Steven Lawrence - Superintendent
Vote Results:  

Original Motion
Member (Linda Mayo) Moved, Member (Lynne Dennler) seconded to approve the Original motion 'Approve Consent Agenda.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion CARRIED 5 - 0