Subject:   9.12 (Item #12) Final Change Order for Bid #1561: New Classrooms at College Park and Concord High Schools
Strategic Plan
Policy:  
Enclosure
File Attachment:  
Summary On April 27, 2010 the Board of Education awarded Bid 1561 to Magnum Construction, Inc. in the amount of $1,654,725.00 for the construction of new SMART classrooms at College Park and Concord High Schools. As a result of a need to address minor, paving, utility infrstructure and other minor scope modifications and adjustments it will be necessary to issue a single, final change order in the amount of $10,894.49. This change order increase reflects a change order increase of less than 1% of contract value. This single, final change order will result in a revised, final contract value of $1,665,619.49. The construction budget for this project was $2,293,850.00.
Funding Proposition 55 Funding
Fiscal Impact $10,894.49
Recommendation Approve final change order as presented.
Approvals:  
Recommended By:
Signed By:
Pete Pedersen - Measure C
Signed By:
Steven Lawrence - Superintendent
Vote Results:  

Original Motion
Member (Linda Mayo) Moved, Member (Lynne Dennler) seconded to approve the Original motion 'Approve Consent Agenda.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion CARRIED 5 - 0