| Meeting Date: |
Tuesday, March 15, 2011 - 7:30 PM |
| Category:
|
Consent Agenda |
| Type:
|
Action |
| Subject:
|
9.12 (Item #12) Final Change Order for Bid #1561: New Classrooms at College Park and Concord High Schools |
|
:
|
|
| Enclosure:
|
|
| File Attachment:
|
|
| Summary:
|
On April 27, 2010 the Board of Education awarded Bid 1561 to Magnum Construction, Inc. in the amount of $1,654,725.00 for the construction of new SMART classrooms at College Park and Concord High Schools. As a result of a need to address minor, paving, utility infrstructure and other minor scope modifications and adjustments it will be necessary to issue a single, final change order in the amount of $10,894.49. This change order increase reflects a change order increase of less than 1% of contract value. This single, final change order will result in a revised, final contract value of $1,665,619.49. The construction budget for this project was $2,293,850.00. |
| Funding:
|
Proposition 55 Funding |
|
Fiscal Impact:
|
$10,894.49 |
| Recommendation:
|
Approve final change order as presented. |
| Approvals:
|
|
Recommended By: |
|
Signed By: |
 |
|
Pete Pedersen - Measure C |
|
|
Signed By: |
 |
|
Steven Lawrence - Superintendent |
|
|
|
|
|
|
|