8.34 (Item 34) Final Change Order for Bid/RFQ #1555
|
LCAP (Local Control Accountability Plan) Goal:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On August 11, 2009 the Board of Education ratified the Award of Bid/RFQ #1555 to Chain Link Fence and Supply, Inc. for $37,476.00 for the installation of fencing improvements at Clayton Valley High School. As a result of several site requested enhancements and scope extensions an additive change order in the amount of $30,503.00 is necessary. This final, additive change order will result in a final contract value of $67,979.00. The budget for this project was $45,000.00
|
Funding:
|
Proposition 55
|
Fiscal Impact
:
|
None
|
Recommendation:
|
Approve final change order as presented.
|