Agenda Item
Meeting Date:
3/25/2013 - 7:30 PM  
Category:
Consent Agenda  
Type:
Action  
Subject:
10.12 (Item #15) Final Change Order - for LLB #1594 for New Chemistry Classroom Construction at Mt. Diablo and Clayton Valley Charter High School  
LCAP (Local Control Accountability Plan) Goal:
 
Policy:
 
Enclosure:
 
File Attachment:
01 - LLB1594 Final Change Order.pdf
 
Summary:
On August 20, 2012 the Board of Education awarded Two (2) Lease/Lease-back Agreements #1594 to Meehleis Modular Buildings, Inc. for $3,598,892.00. Lease agreements constituted all tools, materials, equipment and labor necessary to construction new five (5) new chemistry classrooms at Clayton Valley and Mt. Diablo High School.

As a result of value engineering and need to: 1)implement site requested post design addition of case-work and fume hood; 3) minor unforeseen utility, electric, mechanical and structural modifications; and 4) return of un-used contingency fund, staff is recommending a single, final DEDUCTIVE change order in the amount of ($96,843.82). This single, final change order constitutes the return of approximately 89% of contingency and 0.31% contract changes and will result in a final contract value of $3,502,048.18.
 
Funding:
Proposition 55  
Fiscal Impact:
($96,843.82)  
Recommendation
Approve Final Change Order as Presented  
Approvals:
Recommended By:
Signed By:
Tim Cody - Program Manager
Signed By:  
Steven Lawrence - Superintendent