Agenda Item
Meeting Date:
12/8/2009 - 7:30 PM  
Category:
Consent Agenda  
Type:
Action  
Subject:
10.18 (Item 20) Final Deductive Change Order for Bid #1534/Contract C-887  
LCAP (Local Control Accountability Plan) Goal:
 
Policy:
 
Enclosure:
 
File Attachment:
 
Summary:
On January 13, 2009 the Board of Education awarded Bid # 1534 to Taber Construction, Inc. for $5,340,950.00 for the provision of the removal of existing mechanical systems and the installation of new heating, ventilating and air conditioning systems at Fair Oaks and Shore Acres Elementary Schools, Pleasant Hill Middle School and Olympic High School. As a result of value engineering and a savings on unit pricing allowances staff was able to negotiate a final deductive change order for $180,886.00. This deductive change order resulted in a final, decreased contract value of $5,160,084.00. The budget for this particular project was $10,232,252.00  
Funding:
Proposition 55 Funds  
Fiscal Impact:
Project savings of $180,886.00  
Recommendation
Approve final deductive change order as presented  
Approvals:
Recommended By:
Signed By:
Pete Pedersen - Measure C
Signed By:  
Richard Nicoll - Interim Sup