Subject:
10.20 (Item 22) Final Additive Change Order for Bid #1547/Contract C-891  
LCAP (Local Control Accountability Plan) Goal:
 
Policy:
 
Enclosure:
 
File Attachment:
 
Summary:
On May 26,2009, the Board of Education awarded Bid #1547 to B Bros Construction, Inc., for the Installation of Playground Improvements at Mt. Diablo, Shore Acres, Sun Terrace, Wren Avenue and Ygnacio Valley Elementary Schools.

As the result of an unforeseen need, 1) to remove excess, decomposed fibar in several over-excavated playboxes, and 2) redevelop grades and bases in these over-excavated areas, it is necessary to issue a single, additive final change order in the amount of $16,084.94. This single, final change order will increase the original contract value of $231,000.00, to a revised, final value of $247,084.94.
 
Funding:
Proposition 55  
Fiscal Impact:
$16,084.94  
Recommendation
Approve Final Change Order as presented  