15.18 (Item #21) Final Change Order to Fort Bragg Electrical, Inc. – Electrical and Low Voltage Services at Concord High School |
|
|
LCAP (Local Control Accountability Plan) Goal:
|
Strategic Initiative 5.3 Optimal Operations and Infrastructure Ensure that our facilities and infrastructure support and enhance student learning and safety.
|
|
|
Enclosure:
|
|
File Attachment:
|
|
Summary:
|
On December 12, 2016, the Board of Education approved contract action for C-943/Bid#1762 to Fort Bragg Electric, Inc. for an electrical power and low-voltage services package to Interim Housing unit placed at Concord High School. As a result of District requested scope addition, a single, final change order in the amount of $5,600.18 is necessary. This final change order will result in a contract value of $110,475.18. |
|
|
Funding:
|
|
Recommendation
|
Approve the Final Change Order to Fort Bragg Electrical, Inc. – Electrical and Low Voltage Services at Concord High School. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Tim Cody - Program Manager |
|
Signed By: |
|
Sharon Ketcherside - Purchasing Consultant |
|
Signed By: |
|
Dr. Nellie Meyer - Superintendent |
|
|
|
|
|
Vote Results:
|
Original Motion | Member Debra Mason Moved, Member Cheryl Hansen seconded to approve the Original motion 'Approve the Final Change Order to Fort Bragg Electrical, Inc. – Electrical and Low Voltage Services at Concord High School.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Linda Mayo | Yes | Joanne Durkee | Yes | Brian Lawrence | Yes | Cheryl Hansen | Yes | Debra Mason | Yes | |
|
|
|
|
|
|